Delivering and placing rebar: from the truck to the job site

Rebar delivery and placing, question by question: truck loading order, placing accessories, spring load restrictions, day-before confirmation, site schedule, crews, placing hours and extras.

MBBy Maxime Beaupré · 6 min

A successful rebar delivery arrives on the right day, at a job site that is ready to receive it, loaded in the order the steel will be placed, with its placing accessories. On site, the ironworkers install the steel according to the drawings. For the company, two things then matter: assigning crews across job sites, and tracking placing hours by job. Extras are also won or lost here.

This guide takes the delivery and placing questions one by one and summarizes, for each, the article that answers it. It expands the delivery and installation section of the complete guide to rebar software.

In what order should the truck be loaded?

A rebar truck is loaded with the way the job site will unload it in mind. Everything depends on one question: will the steel be placed straight off the truck, or unloaded on site? In the first case, what will be placed first goes on top, then you work down following the placing order. In the second, a few of the first pieces to place usually go on top, and the rest is loaded in reverse placing order: once the truck is empty, the next piece to place ends up on top of the pile.

The article on rebar truck loading order gives an example: part of the bottom mat of a structural slab rides on top, the crew places it first, then unloads the rest of the steel onto it. It points out the limit of this order, stability: when placing order and stability conflict, stability wins. It also covers grouping bundles (one delivery per phase, the bundles of one element together, one mark per bundle), tags that must stay readable without disturbing the load, and the check against the bar list before the truck leaves.

When everything does not fit, a partial delivery is not a problem in itself. The part that leaves must contain what the crew needs next, in placing order, so the job site is never held up. The site foreman, the shop foreman and the detailer must know before the truck arrives.

Why must placing accessories leave on the right delivery?

A truck can arrive with all its bundles, properly tagged, in the right order, and still leave the placing crew standing around: all it takes is missing chairs. The article on placing accessories explains where they are found. Some are rebar themselves and are on the bar list: support bars, type 25 chairs, wall spacers. Bars delivered with couplers appear there as special items. The other accessories are planned with the delivery.

Either way, each accessory must leave on the right delivery and be checked at loading, the last moment when a miss costs almost nothing. The detailer plans the right quantity for each delivery; when the site foreman thinks they will run short, they are the one who calls the detailer. A miss costs hours: a crew waiting, an extra trip, and a crane that may already have moved on to another trade or another job site.

What do spring load restrictions change for deliveries?

Every spring, in the cold regions of Canada and the northern US, the loads allowed on heavy vehicles are reduced during the thaw, often zone by zone or road by road, on dates that vary with the weather. For a rebar company, that means less steel per truck, more trips and a tighter schedule. The article on spring load restrictions and rebar deliveries points to your provincial or state transportation department, or local road authority, for this year's dates, zones and limits: don't rely on last year's.

Among its answers: deliver before the restrictions when the job site can receive and store the steel properly, lighten loads during them, and warn the job site early. The problem is solved when the bar lists are split, not the day before the delivery. A load split by weight, without looking at placing order, delivers pieces of elements: each lightened load must stay usable on its own, placing accessories included.

Why confirm the delivery the day before?

Because the job site changes faster than the plan. A postponed pour, a crane booked by another trade, a blocked access: if nobody told the shop, the truck arrives for nothing. The article on confirming the delivery the day before starts from a simple rule: confirm every delivery the day before, with the customer for a first delivery or a first day of placing, with the site foreman as soon as there is one on site.

The call also checks what shapes the load: has the placing order changed, will the crew place straight off the truck or will the steel be unloaded on the ground, where do access and the crane stand? It is also the time to say what will be missing if the delivery is partial. And one rule helps plan the day: job sites that are starting receive their steel early in the morning; a job site already underway, which already has steel to work with, can receive its delivery later in the day.

How do you follow the site schedule and the other trades?

On a concrete job site, rebar arrives in the middle of the line: the formwork crews go before, the concrete comes after. Delivered too late, it holds everyone up. Delivered too early, it clutters the job site: the steel is unloaded in a tight space, moved once or twice, bundles get mixed up and tags get damaged.

The article on coordinating with the site schedule asks you to plan according to the real state of the job site, not only according to what was planned. It shows that this coordination starts at detailing: a project split into phases that follow the way the job site will progress delivers well. It also goes through the shop foreman, who must hear about a schedule change early, and through the other trades, with whom crane time is shared.

How do you assign ironworkers across job sites?

It is a decision to make again every day, because job sites never progress exactly as planned: formwork running late, a pour moved up, a delivery postponed. In the article on assigning ironworkers, it is the real state of the job sites the day before that decides where crews will be useful the next day. A badly placed crew costs paid hours with no steel placed: the formwork is not closed, the steel has not arrived, or the chairs and supports are missing.

Crew assignment depends on delivery, especially in spring, when load restrictions push deliveries back: a placing crew with no steel is useless, and a truck of steel with no crew clutters the job site. And when an ironworker changes job site during the day, their hours must follow.

Why track placing hours by job?

Because the bid was only a forecast: placing hours recorded by job tell you what the project really cost. These hours are the basis for the next bids. The article on placing hours by job points out that they depend on the number of pieces and their bending complexity, not only on weight.

To make them useful, it recommends recording them every day, by job and by element, separating waiting, unloading and extras, then comparing actual to estimate, job after job, in the same categories as the bid. How to use them for estimating is covered in estimating rebar placing in hours per tonne.

Why record extras on site, the same day?

An extra is the difference between the work shown on the bid drawings and the work that must be done or has been done. It is almost always lost on the job site, not in the office. The most common case is also the quietest: the ironworker adapts the steel on site without writing anything down, and the work is done for free.

The article on extras on site explains why the note cannot wait: once the concrete is poured, the proof is gone. It splits the roles. The ironworker reports what they changed, without deciding whether it is an extra; the site foreman records it the same day, with a photo before the pour; the office then compares against the bid drawings. What happens next, in the office, is covered in billing and negotiating rebar extras.

What is the next step?

Billing and accounting: billing everything that was delivered and placed. It is the ninth step of the complete guide. The previous step, production and fabrication, takes up the seventh section.

Metacis is rebar software built by people in the trade. If these questions come up in your company, let's talk: request a demo.