Rebar arrives between formwork and concrete: too early, it clutters the site; too late, it blocks everyone. Why tie deliveries to the site's real progress.

MBBy Maxime Beaupré · 5 min

On a concrete job site, rebar arrives in the middle of the line. The formwork crew goes first, the concrete comes after, and other trades often wait for the steel to be in place before doing their part. Delivered too late, it blocks everyone. Delivered too early, it clutters a site that has no room to store it. Coordinating rebar with the site schedule isn't a refinement: it's the condition for the steel to be placed when it has to be.

I spent ten years on the shop floor and on job sites as a detailer and ironworker, and I've been programming for more than 30 years. This article explains why coordination with the site is decided long before the truck, and why it depends as much on the shop and on detailing as on the site itself. To see where delivery fits in the trade as a whole, see the complete guide to rebar software.

Why does rebar depend so much on the site schedule?

Because it can't be placed before the site is ready, or after the others are waiting for it.

Before the steel, the formwork has to be in place, or at least far enough along to work in. After the steel, there are often other trades that have to go through, an inspection, then the concrete. One day's delay on the rebar can push that whole sequence back. And a concrete pour, with the mixer trucks and the pump booked, isn't easily moved.

That's what makes rebar different. Many materials can wait on a job site. Rebar is expected at a specific time, by a specific crew, for a specific element.

What does steel delivered too early cost?

People often think it's better to be early than late. For rebar, it isn't that simple.

A site that receives its steel too early has to unload it somewhere. In the city, space is scarce: the steel ends up on a corner of the lot or on a slab already poured, in everyone else's way. It will have to be moved once, then a second time, often without a crane. Bundles for different elements get mixed up, tags get damaged or lost, and when it's time to place, the crew searches instead of placing.

That's why the site's storage capacity matters as much as its date. A site that only has room for one delivery at a time shouldn't receive two, even if the shop is ready.

What does steel delivered too late cost?

The most obvious: a crew of ironworkers waiting, paid without placing. But the real cost is often elsewhere. The formwork is ready and tied up. The pour, already booked, has to be postponed. The trades that were to follow the steel reorganize their day, or leave. And the general contractor will remember who delayed the job.

So a rebar delay is almost never just a rebar delay. It's a delay for everyone who comes after.

Why talk about the real state of the site, and not its schedule?

Because the schedule is what was planned, and the real state is what's happening.

Deliveries are often planned weeks ahead, based on the site schedule, the construction phases and the truck capacity. The site, meanwhile, falls behind because of rain, formwork that takes longer than expected, an inspection that's moved. Sometimes it also gets ahead and asks for the steel sooner.

A delivery tied to a schedule that's no longer true arrives at the wrong time. That's why the rule of confirming the delivery the day before, with the client for a first delivery, then with the foreman once he's on site, is so important: it's the last moment to check that the site really is ready, that the space is free and that a crane will be there.

Why does coordination start at detailing?

Because the detailer is the one who splits the steel into possible deliveries.

When the detailer prepares the bar lists, he already takes into account the site schedule, the construction phases and the truck capacity. A project split into phases that follow the way the site will progress delivers well. A project detailed in one block, or in phases that no longer match the site, forces the shop to separate deliveries at the last minute.

So the information has to travel back. When the site changes the order of its work, the detailer has to know for what remains to be detailed and delivered. When a delivery is partial, the detailer has to know as well, and the part that leaves has to contain what the crew needs next, in placing order. The article on loading order covers this in more detail.

Why does the shop need to know the site schedule?

Because it produces with a limited capacity, and it can't do everything the day before.

Deliveries are slotted into a production calendar, spread out according to what the shop can produce each day. If the shop foreman learns of a change to the site schedule at the last moment, he has to shake up production, and it's often another job that pays the price. If he learns of it early, he reorganizes without drama.

A fabrication shop that only knows the promised dates, and not the real state of the sites, produces steel that will wait in the yard while other sites wait for theirs.

Why do the other trades change everything?

Because the rebar crew never works alone on a site.

The formwork crew, the electricians and plumbers running conduits through a slab, the inspection, the concrete: each has its place in the sequence. When one of them falls behind or changes the order, the rebar has to follow. Crane time is shared among these trades, and a truck of steel that arrives while the crane is lifting formwork panels is going to wait.

These changes also have consequences beyond the delivery. A crew moved from one site to another because a trade wasn't ready is a matter of assigning ironworkers across job sites. Hours lost waiting distort placing hours by job. And steel that has to be redone because another trade changed something may be an extra, to be written down on site the same day.

Where does coordination break down most often?

  • The site changes, and the shop doesn't know. The truck leaves according to a plan that's no longer true.
  • What's ready gets delivered, not what's expected. The steel that came out of production isn't necessarily what the site places next.
  • Space is forgotten. The site has no room to store two deliveries.
  • The detailer isn't in the loop. The phases no longer follow the way the site is progressing.
  • The information goes through one person. When that person is away, nobody knows where the site stands.

Coordinating rebar with the site means circulating the same information between detailing, the shop, the yard and the site, from drawing to invoicing. When that information is retyped from one file to another or stays in a phone, the gap is often discovered in front of the site. If you're comparing software, the guide on how to choose rebar software gathers the questions to ask about these handoffs between steps.

Metacis is rebar software built by people in the trade. If your deliveries are giving you headaches, let's talk: request a demo.

Share

Frequently asked questions

Related articles

Metacis is rebar software designed by people in the trade.