A rebar truck at a site that isn't ready is a wasted trip. Why confirm every delivery the day before: client for a first delivery, then the site foreman.
A rebar truck shows up at 7 a.m. at a job site. The planned pour has been postponed, the crane is booked for another trade, or the foreman simply has no crew that day. Nobody told the shop. The truck leaves still loaded, or it unloads wherever it can, and the steel ends up in everyone's way. One simple rule prevents most of these wasted trips: always confirm the delivery the day before, with the client for a first delivery and with the site foreman once one is on site.
I spent ten years on the shop floor and on job sites as a detailer and ironworker, and I've been programming for more than 30 years. There's nothing technical about this rule. Yet it's one of those that make the most difference to the real cost of deliveries. This article explains why. To see where delivery fits in the trade as a whole, see the complete guide to rebar software.
Because deliveries are planned at the shop, and reality changes on site.
A delivery date is often decided days or weeks ahead, between the project manager, the foreman and the client, taking into account the site schedule, the construction phases and the truck capacity. Then the site lives its own life. It rains, the formwork falls behind, an inspection is moved, another trade takes up the space planned for unloading. None of that news travels to the shop by itself.
The result is familiar to anyone who has made deliveries: a truck in front of a closed gate, a driver waiting for someone to answer the phone, steel unloaded in the wrong place that will have to be moved twice.
More than the trip.
There's the driver and the truck, tied up for nothing. There's the next delivery, which doesn't leave on time because the truck isn't back. There's the steel that comes back to the yard and has to be unloaded, put away and reloaded. And there's the site that was supposed to receive its steel that day and is waiting, because the truck was somewhere else.
A call the day before takes a few minutes. It doesn't solve everything, but it catches most changes before the truck is loaded, at a point when it's still easy to reorganize the day.
With someone who knows what will happen on site the next day. For a first delivery or a first day of placing, that's the client. When a foreman is on site, he's the one you coordinate with.
This matters. A confirmation given by an office that hasn't seen the site in a week isn't worth much. Once on site, the site foreman knows whether the formwork is ready, whether his crew will be there, whether the crane will be free and where the truck can set up. From then on, his information is the one that counts.
The answer also has to get back to the right person at the shop. A confirmation received by the driver or by the front desk, that never reaches the person preparing the load, is useless.
Because a site that's just starting has nothing to place until the steel arrives.
The usual rule is simple: sites that are starting get their steel early in the morning, and sites in progress get it later. A site in progress already has steel on site; its crew can work in the morning and receive the rest during the day. A new site has a crew waiting in front of an empty space. Every hour the truck is late is an hour paid with no placing.
This rule helps put the trucks' day in order. It also makes the day-before confirmation even more important for new sites: if the 6:30 a.m. truck finds a closed gate, the whole run slips.
The delivery itself, first: does the site still want the steel tomorrow, and at what time?
Then, what shapes the load. Has the placing order changed? Will the crew place straight off the truck, or will the steel be unloaded on the ground? That changes the order in which the truck has to be loaded, as the article on loading order explains. Will there be a crane, and at what time? Where can the truck set up? Is the access clear?
Placing accessories, though, aren't settled during this call. Chairs and supports leave with the delivery, whether or not they appear on the bar list: the detailer plans the right quantity when he prepares the delivery, and the site foreman calls the detailer if he thinks he'll run short. The article on placing accessories explains why forgetting them costs so much.
It has to be said during the call, not left to be discovered at unloading.
A mark that's late, a bundle that no longer fit under the weight limit, a piece to be redone: a partial delivery isn't a problem in itself. The problem is the site finding out when it opens the truck. The part that leaves has to contain what the crew needs next, in placing order, so the site is never blocked. And the detailer has to be told, so that what remains to be delivered takes into account what actually left.
In the spring, where seasonal load restrictions apply, these separate deliveries become more frequent. The article on spring load restrictions covers this in more detail.
Confirming the delivery the day before is a simple gesture that nevertheless depends on a lot of information: the list of the next day's deliveries, the right contact for each site, what's ready in the yard, what's missing. When that information is scattered across sheets, phones and emails, the gap is often discovered on site. Rebar software that follows the project from drawing to invoicing keeps that information in one place. If you're comparing software, the guide on how to choose rebar software gathers the questions to ask.