Assigning ironworkers means deciding every day who places what and where, based on the real state of the sites, the deliveries and the pours. Why it matters.
Assigning ironworkers across job sites means deciding every day which crew places what, and where. The week's plan isn't enough: formwork that's late, a pour moved up or a delivery postponed changes everything. A good assignment starts from the real state of each site the day before, and it avoids the worst cost in placing: hours paid while nobody is placing steel.
This article is part of the delivery and installation step of our guide to rebar software and the complete steel chain. It's for placing contractors and for fabrication shops that also place the steel they fabricate.
Because rebar placing depends on everyone who comes before it. The ironworker can't start until the formwork is ready and the steel is delivered, and he has to be finished before the concrete arrives. Between those two constraints, there's often little margin.
A company with a few sites open at the same time therefore has to answer the same question every evening or every morning: where will each crew really be useful tomorrow? It's not a decision made once per project. It's a daily decision, remade as the weather, the other trades' delays and last-minute changes dictate.
In the rebar chain, installation in fact involves two distinct needs: assigning the workers, and tracking their hours. The first determines whether paid time becomes placing time. The second lets you know, after the fact, what each job really cost.
Hours paid with no steel placed. The situations are familiar:
The cost isn't only financial. A site that sees the placing crew arrive late or leave too early loses confidence, and you'll face that relationship again at the next bid.
On the real state of each site, not on the original site schedule. For each open site, four questions are often enough to sort things out:
Then come the finer constraints: the distance between sites, the experience required for complex work, an ironworker who has to supervise an apprentice. Ironworkers' working conditions, travel expenses included, depend on any applicable collective agreement and the rules where you work; check them at the source rather than relying on habit.
Because a placing crew without steel is of no use, and a truck of steel without a crew clutters the site. The two decisions are often made by different people: the delivery at the shop or the office, the assignment by the person in charge of placing. When they don't talk to each other, the steel arrives on Wednesday and the crew on Tuesday.
The link is especially strong in the spring, where seasonal load restrictions limit the loads on certain roads and deliveries are postponed: each postponement can free up a crew, or leave it without work. See spring load restrictions and rebar deliveries.
More broadly, assigning crews is the logical next step after coordinating deliveries with the site schedule: the site schedule says what should happen, the assignment says who will be there to do it.
Because a site never progresses exactly as planned. The week's plan is a good starting point, but it ages fast: one day of rain, an inspector who asks for a correction or a formwork crew that's late is enough for half the crews to have to change places.
From one day to the next, though, most crews stay where they were. What changes is a few exceptions. So the difficulty isn't replanning everything, but seeing quickly what has moved, and warning the right people in time. An ironworker who learns at six in the morning that he's changing sites has already lost part of his day.
That's also why the assignment shouldn't depend on one person. If all the information is in the head of the person in charge of placing, an absence or a day off is enough to disorganize every crew.
Because the assignment says who was supposed to be where, and the hours say who was really there, and for how long. When an ironworker changes sites during the day, his hours have to follow. Otherwise, one job seems to have cost less than it really did, the other more, and both give a false picture for the next bids.
The same reasoning applies to extras: a crew moved to another site takes with it the memory of what it adjusted the day before. If the extra wasn't written down before the crew left, it's often lost. See writing down extras on site, the same day and placing hours by job.
Metacis is rebar software built by people in the trade. If this question comes up in your company, let's talk: request a demo.
Share
Metacis is rebar software designed by people in the trade.