A rebar extra that isn't written down on site the same day is often lost: once the concrete is poured, the proof is gone. What to note, who notes it, and why.
A rebar extra is almost always lost on site, not in the office. It's the difference between the work shown on the bid drawings and the work that has to be done or has been done, and the only proof that it happened is in the steel, until the concrete covers it. Written down the same day, with a photo and a few numbers, it can be billed. Forgotten, it's done for free.
This article is part of the delivery and installation step of our guide to rebar software and the complete steel chain. It covers what happens on site, at the moment the extra comes up. The billing and negotiation that follow are covered in billing and negotiating rebar extras.
Because that's where they start, and nobody on site is paid to write. The placing crew is there to place the steel before the pour, not to fill out paperwork. When a problem comes up, the reflex is to fix it and keep going.
One common case, and the quietest: the ironworker adapts the steel to the site without writing anything down. Formwork that isn't exactly where it was supposed to be, an opening that moved, a bar that doesn't fit, an anchorage to redo. He cuts, bends, adds or moves whatever it takes for the work to be right, and he goes on to the next thing. The work is done, often well done, but nothing makes it possible to bill it. If nobody writes it down, the company has just given away those hours and that steel.
The other sources of extras on site look alike:
In every case, it's on site, that day, that people know what was done. The next day, they half remember. The following week, the concrete is poured.
Because a rebar extra has an expiry date: the pour. As long as the steel is visible, it can be photographed, counted and shown to the general contractor's representative. Once the concrete is in place, all that's left is each person's word.
Three other reasons point the same way:
Whoever sees it reports it, and the site foreman writes it down. The most useful rule is simple: the ironworker doesn't have to decide whether it's an extra. He doesn't know the bid drawings, and that isn't his role. He says what he changed, and why.
It's then up to the office, or to the person who prepared the bid, to compare it with what was planned. Some changes will be within the scope of the contract, others won't. But you can only sort what was written down, and a foreman who waits to be sure before writing will often see the concrete arrive before the certainty does.
Enough for someone in the office to understand without calling you. The full file is put together later; on site, you need the raw facts:
The rest (revision reference, comparison with the bid drawings, weight by bar size, before/after sketch) is completed in the office. What goes into an extra file that's ready to present is detailed in billing and negotiating rebar extras.
Because on site, the note competes with the work. If writing down an extra takes longer than doing it, it won't be written down. It's a matter of habit far more than of goodwill.
A few principles make the note realistic:
An extra note becomes valuable when it connects to the rest: to the bar list and the tags of the pieces affected, to the day's placing hours, to the drawing revision, then to the invoice. That's the logic of the whole chain, from drawing to invoicing.
The hours spent on an extra also have a second life: if they're mixed in with the regular hours, they distort what the job appears to have cost, and therefore the next bids. That's one of the reasons to track placing hours by job while separating planned work from added work.
Finally, many extras come from a lack of coordination with the other trades or from a site that wasn't ready. Reducing them at the source also means coordinating deliveries with the site schedule.
These habits cost a few minutes a day. The extras they recover are often work already done, already paid for in wages, that only needed a record to be billed.