Writing Down Extras on Site, the Same Day

A rebar extra that isn't written down on site the same day is often lost: once the concrete is poured, the proof is gone. What to note, who notes it, and why.

MBBy Maxime Beaupré · 5 min

A rebar extra is almost always lost on site, not in the office. It's the difference between the work shown on the bid drawings and the work that has to be done or has been done, and the only proof that it happened is in the steel, until the concrete covers it. Written down the same day, with a photo and a few numbers, it can be billed. Forgotten, it's done for free.

This article is part of the delivery and installation step of our guide to rebar software and the complete steel chain. It covers what happens on site, at the moment the extra comes up. The billing and negotiation that follow are covered in billing and negotiating rebar extras.

Why is the site where extras get lost?

Because that's where they start, and nobody on site is paid to write. The placing crew is there to place the steel before the pour, not to fill out paperwork. When a problem comes up, the reflex is to fix it and keep going.

One common case, and the quietest: the ironworker adapts the steel to the site without writing anything down. Formwork that isn't exactly where it was supposed to be, an opening that moved, a bar that doesn't fit, an anchorage to redo. He cuts, bends, adds or moves whatever it takes for the work to be right, and he goes on to the next thing. The work is done, often well done, but nothing makes it possible to bill it. If nobody writes it down, the company has just given away those hours and that steel.

The other sources of extras on site look alike:

  • A verbal request from the superintendent or the general contractor, made in passing, so the pour isn't delayed.
  • Another trade that forces part of the placing to be undone and redone: a conduit, a sleeve, a duct that arrives after the steel.
  • Waiting: the crew is on site, but the formwork isn't ready.
  • A revision received late, applied directly on site with the steel at hand.

In every case, it's on site, that day, that people know what was done. The next day, they half remember. The following week, the concrete is poured.

Why "the same day" and not at the end of the week?

Because a rebar extra has an expiry date: the pour. As long as the steel is visible, it can be photographed, counted and shown to the general contractor's representative. Once the concrete is in place, all that's left is each person's word.

Three other reasons point the same way:

  • Memory fades fast. After a day of placing, the details of a morning adjustment are already blurry. After a week, nobody knows whether it was the north wall or the east wall.
  • Crews move. The ironworker who did the work may be on another job the next day. The person who knows is no longer there to say so.
  • A verbal request is easier to confirm while it's fresh. A short message the same day, along the lines of "further to your request this morning, we added…", is hard to dispute. The same message sent three weeks later, at billing time, is much less so.

Who should write down the extra on site?

Whoever sees it reports it, and the site foreman writes it down. The most useful rule is simple: the ironworker doesn't have to decide whether it's an extra. He doesn't know the bid drawings, and that isn't his role. He says what he changed, and why.

It's then up to the office, or to the person who prepared the bid, to compare it with what was planned. Some changes will be within the scope of the contract, others won't. But you can only sort what was written down, and a foreman who waits to be sure before writing will often see the concrete arrive before the certainty does.

What should you note, at a minimum?

Enough for someone in the office to understand without calling you. The full file is put together later; on site, you need the raw facts:

  1. What changed, and where. The element, the gridline, the level: "foundation wall, east side, between two gridlines".
  2. The pieces affected. The tags or marks of the bars that were cut, bent, added or removed. The tag is what ties the steel on site to the bar list it comes from and to the drawing: without it, the office will have to guess which bars you mean.
  3. The quantities. Say it plainly: "20 bars of 15M (≈ #5), 3 metres long, added", "12 unplanned drilled holes".
  4. The time. How many ironworkers, for how long, including waiting.
  5. Who asked for it, and when. The person's name or role, and the time.
  6. A photo before the pour. If possible with a visible reference point. It's often the most convincing item in the future file.

The rest (revision reference, comparison with the bid drawings, weight by bar size, before/after sketch) is completed in the office. What goes into an extra file that's ready to present is detailed in billing and negotiating rebar extras.

Why will a note that's hard to take never be taken?

Because on site, the note competes with the work. If writing down an extra takes longer than doing it, it won't be written down. It's a matter of habit far more than of goodwill.

A few principles make the note realistic:

  • It has to be possible to take it on the spot, standing up, with gloves within reach, not in the evening at the office.
  • It has to be short. Five lines and a photo are better than a two-page form that stays in the truck.
  • It has to end up somewhere. A note that stays in the foreman's phone or in a notebook doesn't exist for the office. It has to arrive in the same place as the rest of the project, attached to the right job.
  • It has to be expected. If nobody in the office ever asks "any extras today?", the crew concludes that it doesn't matter.

How does the extra noted on site join the rest of the chain?

An extra note becomes valuable when it connects to the rest: to the bar list and the tags of the pieces affected, to the day's placing hours, to the drawing revision, then to the invoice. That's the logic of the whole chain, from drawing to invoicing.

The hours spent on an extra also have a second life: if they're mixed in with the regular hours, they distort what the job appears to have cost, and therefore the next bids. That's one of the reasons to track placing hours by job while separating planned work from added work.

Finally, many extras come from a lack of coordination with the other trades or from a site that wasn't ready. Reducing them at the source also means coordinating deliveries with the site schedule.

Which habits should you start tomorrow?

  • The ironworker reports every change made to the steel, even a small one, without judging whether it's billable.
  • The site foreman writes down the extra the same day, with a photo before the pour, and confirms every verbal request in writing.
  • The office asks for extras every day or every week, compares them with the bid drawings and puts the file together.

These habits cost a few minutes a day. The extras they recover are often work already done, already paid for in wages, that only needed a record to be billed.

Metacis is rebar software built by people in the trade. If this question comes up in your company, let's talk: request a demo.

Share

Frequently asked questions

Related articles

Metacis is rebar software designed by people in the trade.