Lump sum: a percentage of the price based on delivered or installed weight. Unit price: the weight and the placing hours. Each contract needs its own proof.
A lump-sum rebar contract is usually billed as a percentage of the total price, based on the actual weight compared with the planned weight. A unit-price contract is billed on what was actually supplied and placed: the weight at the unit price, and the placing hours at the agreed rate. In both cases, the weight billed is the delivered weight for a supply-only contract, and the installed weight for a supply-and-install contract. The proof you have to provide, however, is not the same.
This article is part of the billing step of our guide to rebar software and the full steel chain. It covers the regular billing of a contract. Extras follow their own rules and are covered in billing and negotiating rebar extras.
Because it decides who carries the risk on quantities. In a lump-sum contract, you committed to a price for the whole scope you bid: if the project needs a bit more steel than your estimate, that's your problem, unless you can show it's an extra. In a unit-price contract, the client committed to prices, not to a quantity: they pay for what was delivered and placed, and they carry the risk on quantities.
That split of risk shows up on every invoice. On a lump sum, the client pays a share of a price already agreed; the question is whether the share billed matches the progress. On a unit-price contract, the client pays for quantities; the question is whether those quantities are right. The same rebar company can have both kinds of contracts running at once, and they aren't managed the same way.
As a percentage of the delivered or installed weight, depending on whether the contract includes placing. The principle is simple when you say it out loud: on a contract planned at 400 tonnes, if 100 tonnes have been delivered or installed by the end of the month, you bill roughly a quarter of the contract price. Next month, another 100 tonnes: another quarter.
What serves as the basis is the bar lists. Each delivery groups bar lists, each bar list has a weight, and the sum of the delivered or installed weights gives the progress. A bar list that was delivered but isn't attached to a delivery, a delivery that never makes it to the office, placing that isn't recorded on site: that's all steel that won't be billed this month.
On a supply-and-install contract, the invoice therefore follows the job site rather than the deliveries. Terms vary a lot from one contract to the next: reread yours before you issue your first invoice.
Because it compares an actual weight with a planned weight, and both move.
None of these gaps is a mistake in itself. They become a problem when nobody sees them coming and they all show up at once in the project's last invoices.
With two lines that don't come from the same place: the weight and the placing hours. The weight comes from the installed bar lists: 30 tonnes placed this month, at the agreed unit price. The placing hours come from the job site: for example, 400 ironworker hours on the project this month, at the agreed rate.
That's where the unit-price contract gets demanding. The client pays for what they can check. For the weight, they compare against the bar lists, the signed delivery slips and what's placed on site. For the hours, they compare against what they saw on site. A placing hour that wasn't recorded the same day, against the right job, is an hour that's hard to bill, and even harder to defend.
Placing hours depend on the number of pieces and how hard they are to install, not only on weight: threaded bars or bars placed in a wall take more hours than those in the bottom of a raft slab. That's why you can't rebuild them after the fact from the tonnes delivered. They're recorded on site, every day: that's the subject of our article on placing hours by job.
It depends on the accessory. Some accessories are rebar themselves: support bars, type 25 chairs, wall spacers. They're fabricated like the rest of the steel, and they're on the bar list. Bars delivered with couplers are on it too, as special items: they need the threading and the coupler. The other accessories are planned with the delivery. Whether an accessory is on the bar list or not, it has to leave with the right delivery and be checked at loading. Whether accessories are included in the price or billed separately depends on your bid and your contract.
The invoice is the last step of a chain that starts at the drawing: the bar list, the tags the shop prints from it and fabricates from, the delivery, the placing. From drawing to invoicing, every link has to pass on what it knows. Before billing, the office should be able to answer these questions without calling anyone:
When those answers are spread between the shop foreman, the site foreman, the detailer and the office, every month-end becomes an investigation. Some of the information arrives late, some never arrives, and that's money left on the table.
If you recorded properly what was delivered and placed, the end of the contract gives you the most useful answer of the whole year: was the price you bid the right one? On a lump-sum contract, you compare the actual weight, delivered or installed depending on the contract, with the estimated weight; on supply and install, you also compare the real cost of placing with what was planned. On a unit-price contract, you compare the actual hours per tonne with those in your bid. Either way, those numbers are what will make your next bid more accurate.
It's also a question to ask when choosing rebar software: how does information travel from the delivery and the job site to the invoice, for a lump-sum contract as well as a unit-price one?