A rebar bar list is the list of every bar in a structure: mark, size, quantity, length, bend shape and weight. What it contains, who uses it, common errors.
A rebar bar list (also called a barlist, or a bar bending schedule in some countries) is the list of reinforcing bars to fabricate for a structure or part of a structure. For each bar it gives the mark, the size, the quantity, the length, the bend shape and the weight. It's what the shop tags are made from, and the tags are what the shop uses to fabricate the bars; after that, the bar list is used on site for placing and in the office for invoicing.
The bar list holds a special place in a rebar company: it turns the drawing into bars to fabricate, and its tags follow the steel from the shop to the jobsite. This article explains what it contains, who prepares it, who uses it, what the tags are for and where errors creep in. To see how it fits into all the steps of a rebar business, see the bar list section of the rebar software guide.
Every company has its own layout, but you almost always find the same information. Each line of the bar list describes a group of identical bars:
Depending on the company and the project, you'll often also find the element or level where the bar will be placed (footing, wall, slab, column), the steel grade, the lap or cover to respect, and notes for the shop or the site. The header identifies the project, the bar list number, its revision and the drawing it comes from.
A bar list normally ends with the total weight per bar size and the grand total.
Here is a fictional, simplified example for a small foundation wall, laid out the way a Canadian bar list would be: bars are grouped by element, the bend type refers to the industry's standard shapes, and columns A, B, C… give the dimension of each segment.
Project: Example — foundation wall · Bar list: 01 · Revision: 0 · Reference drawing: D-01
| Mark | Qty | Size | Length (mm) | Type | A | B | C | D | E | F | G | Mass (kg) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Footing | ||||||||||||
| 01 | 6 | 20M | 6,000 | 85 | ||||||||
| 02 | 30 | 15M | 1,300 | 17 | 150 | 1,000 | 150 | 61 | ||||
| Wall | ||||||||||||
| 03 | 40 | 15M | 2,650 | 2 | 250 | 2,400 | 166 | |||||
| 04 | 14 | 15M | 6,000 | 132 | ||||||||
| 05 | 8 | 15M | 1,200 | 2 | 600 | 600 | 15 | |||||
| Total 15M | 374 | |||||||||||
| Total 20M | 85 | |||||||||||
| Grand total | 459 |
Fictional example, for illustration only: the project, quantities and dimensions are made up. The marks aren't real marks; they only number the lines. Marking conventions vary from one company to another, and there are much more efficient ways to mark bars. Masses are calculated with the CSA masses per metre and rounded to the kilogram.
A real bar list is longer and has more columns, but it reads the same way: one line per mark, each mark points to a specific place on the drawing, and each line will become one or more tags at the shop.
The bar list is first the detailer's work. Working from the engineer's structural drawings, the detailer produces the placing drawings and the list of bars that comes out of them. It's a job of judgment: you have to apply laps, hooks and cover, break lengths so they can be fabricated and shipped, and catch the errors or omissions in the original drawings. Sometimes someone at the shop also prepares a bar list without a drawing, for a few pieces or a simple order.
After that, the bar list goes through a lot of hands:
Don't confuse it with the approximate bar list the estimator prepares at bid time to set a price: the fabrication bar list has to be exact, down to the last bar.
On a project of any size, the steel isn't put on a single bar list. The detailer or the project manager splits it into several bar lists according to the schedule, the construction phases and the shipping constraints, so that each shipment matches what the site can place.
The bar list doesn't go down to the shop floor as is. It becomes tags: each line produces one or more tags, which carry the mark and what's needed to fabricate and recognize the bar. From that point on, it's the tag, not the bar list, that travels with the steel.
The tag is used at every step. At the shear and the bender, it tells the operator what to produce. At bundling, it identifies the bundle. At loading, it lets you check that the right bundles go on the right truck. On site, it lets the ironworkers know which mark each bundle belongs to and where it goes, without pulling the pile apart to measure the bars.
That's why a bar list error never stays on paper: it is reproduced on the tags, and then on the steel. A tag that's lost, unreadable or printed from an old revision leaves a bundle with no reliable identity, and someone then has to figure out by hand what it is and where it goes. Many shops add a barcode to their tags to track each bundle from cutting to loading.
The drawing and the bar list describe the same reinforcing steel in two ways. The placing drawings show where each bar goes in the structure. The bar list says what has to be fabricated. The link between the two is the mark: bar 05 on the drawing is line 05 on the bar list, and then tag 05 on the bundle that arrives on site.
A bar list that no longer matches its drawing is wrong, even if every line looks right. The drawing and the bar list should therefore always carry the same revision number, and the site should know which version it has in hand without having to call the office.
The mark is a bar's name. It designates a single type of bar: same size, same shape, same dimensions. As soon as any one of those changes, you need another mark.
There's no single marking system. Some companies number by element (wall, footing, slab), others build the mark from the size and the shape. What matters is that a mark designates a single bar across the whole project, that everyone reads it the same way, and that it stays the same from the drawing to the site. Two different bars under the same mark is a guarantee that one of them will be fabricated or placed wrong.
A bent bar can't be described with a single length. The bar list gives a bend type and the dimension of each segment. So that the shop and the detailer speak the same language, the industry uses standard, numbered shapes, defined in Canada in the Reinforcing Steel Institute of Canada (RSIC) Manual of Standard Practice, and in the US in the CRSI Manual of Standard Practice. They include, among others, hooked bars, L and U bars, open and closed stirrups, and spirals.
Using these standard shapes means you don't have to draw every bend. When a bar doesn't match any standard shape, it has to come with a dimensioned sketch. The way segments are dimensioned and the cut length is calculated also follows conventions. If the detailer and the bender operator don't read a dimension the same way, the bar will be off by a few centimetres, and it won't fit in the formwork.
The weight of a line is simple to work out: you multiply the number of bars by their length and by the mass per metre of the bar size. Those masses per metre come from the standard that governs reinforcing bars (in Canada, the CSA standard). Each bar size has its own mass, and it's always the one from the standard you should use, not a value rounded from memory.
Weight isn't a detail: it's used to order steel, plan the shop, load the trucks and invoice, since a lump-sum contract and a unit-price contract both rely on weight. A weight typed in by hand rather than calculated, or calculated with the wrong mass, throws off everything that comes after it.
The original drawings are rarely final. An RFI to the engineer, a change from the architect or an error found on site, and the drawing changes. That change has to make its way to the bar list, the shop and the site, and information can get lost at every handoff.
Three situations come up often:
A revised bar list should always say clearly what changed, on what date and according to which drawing revision. And before sending a revision to the shop, the first question to ask is simple: has this steel already been produced?
Bar list errors rarely come from a lack of skill. They mostly come from information that's retyped, copied or passed from one tool to another. The most common:
A bar list error is often only discovered on site, when the steel is already cut, bent, tagged and delivered. The bar list is therefore the place where the specifics of rebar (sizes, shapes, laps, masses per metre, revisions) have to be right, before the steel enters the shop. Rechecking them by hand, line by line, every time the information moves from one tool to another is tedious: the less it's retyped, the fewer chances there are to make a mistake. On bar lists built in a spreadsheet, and the tools used to prepare them, see also how to choose rebar software.